The AquaDam®s were in place for approximately 30 days. The slab was pored concrete until it reached the water line. Then multiple large slabs were placed below the water line. This was why no dewatering had to take place during this project.
Grants Pass, OR
Large rip-rap (rocks) were placed on the upstream side of the concrete slab boat ramp. Smaller rocks were placed on the downstream side. During high flows in the winter this will protect the concrete slab from washing out.
Grants Pass, OR
Another view of the new boat ramp. This backhoe equipment will help us in removing the AquaDams®.