Stream Diversion for Concrete Check Dam
Medford, OR (2002)
Page 1 of 3
A concrete check dam was constructed midstream to force water into an existing intake structure. The water flow had to be diverted before the concrete could be poured. In the past, a check dam was constructed by machinery out of gravel, but this is no longer environmentally acceptable.
Medford, OR
To ensure that a good seal is achieved, all large rocks must be removed from the path of the AquaDam®. In this case, the rocks were placed in such a way that they helped support the AquaDam® once it was installed.
Medford, OR
A view of the intake structure.
Medford, OR
A view from the intake structure, looking upstream at the AquaDam®.
Medford, OR
A testimonial from the satisfied customer can be viewed by clicking here.