Lake Independence, California 2012
15' deep Intake Channel Isolation

Click on photos to view a larger version
A 1' tall AquaDam was placed below the primary AquaDam. It was filled after the primary AquaDam was fully inflated. Its purpose is to better conform to the rocky channel bottom, reducing potential seepage into the work area. Lake Independence, California 2012
The primary AquaDam continues to unroll. The 1' AquaDam is visible, coming back over the roll. Lake Independence, California 2012
The sides of the primary AquaDam were folded in before being rolled up, to fit on the trailer. Now as the AquaDam fills and unrolls, the sides of the AquaDam will unfold to its full width of 44' Lake Independence, California 2012
Lake Independence, California 2012
The 1' under-dam was just long enough to reach waters edge at the far end. The sides of the primary AquaDam continue to unfold. Lake Independence, California 2012
A 4-man filling procedure was devised and implemented to allow safe, contained refueling of the 3" water pumps. Lake Independence, California 2012
Lake Independence, California 2012
Lake Independence, California 2012
The 21' tall primary AquaDam is fully unfolded and has a head above water level. Lake Independence, California 2012