Wetlands Protection
Everglades National Park
FL (2006)
Page 1 of 5
This was the 5th National Park project for Aqua Dam, Inc.. We have completed projects in Redwood National Park, Glacier National Park, Great Smoky Mountains National Park, Yosemite National Park, and now Everglades National Park.
Everglades National Park, FL
The purpose of this project was to block off part of the Everglades National Park from a dredging operation to take place nearby. This was the first of multiple AquaDams® installed to create a continuous 725' of 4' high dams.
Everglades National Park, FL
The water depth was supposed to be 12 inches. However, the contractor failed to factor in 3 man-made channels that were over 4' deep. We were able to put the AquaDams® through the first two channels, but the third channel was 7' deep.
Everglades National Park, FL
Installing the first 100' x 4' AquaDam®.
Everglades National Park, FL